Gannt Diagram Tutorial Objective:
Instruct an effective mechanism to display slippage of a project task on a different row of the Gannt Diagram based upon the set schedule without updating the start date of the task:
Using a project plan which has baselined alread:
A assignment is forecasted to kickoff on 10/22 finishing on 10/24. As of today, 10/27, the WBS items have not started.
The completed Gannt should display:
- Baseline begin 10/22 - baselined ending 10/24
- Projected begin 10/27 - ending 10/29.
How to make it:
The first step is to perform schedule maintenance in Microsoft Project so that:
- No unstarted work remains earlier than the Status Date
- No work remains unfinished having a finish date earlier than the Status Date.
- No Actual Begin Date is later than Status Date.
- No Actual Start is later than Status Date.
Without having Project using % Completed when running schedule maintenance, MS Project can't tell the best way to help you.
Here are a couple things you can do to output the targeted Gannt view:
- View/Tracking Gannt:
Project presents a view with the Gannt bars for both baseline and current schedule forecast in order.
- Select Format/Gannt Chart Wizard:
Select Baseline and run from there.
- Tools/Tracking/Update Project:
Select the menu item to reschedule incomplete work so that it starts after mm/dd/yyyy
Fortunately, Microsoft Project provides the status date through the process.